May 16, 2009 Update

On May 16 with a good crew of volunteers (mostly from St. Mary’s in Chelsea), the following work was done:
Front bedroom painted with final coat paint
Living room painted with primer
Trees were trimmed in the backyard.
Shed was moved onto the pre-poured pad
Hardware attached to the shed doors
Added flashing and secured frame around exterior of front door

One volunteer (Jay) took the job of removing old insulation, debris and dirt from the crawl space under the back bedroom. It was an extremely dirty and confining job; braving a mammoth woodchuck and bees. He’s to be commended. Hopefully he will return next week to add new visqeen and insulation.

Lunch was brought by one of the volunteers, thank you Mary Ward.

After lunch I left to see my Daughter and Son receive their 2nd degree black belts. Chuck Yonka filled in for me. Thanks, Chuck.

Please pass the word, we need Saturday work slots filled with volunteers.

Thanks for your continued support.
Steve Polgar