Catholic House 2011
Progress Report, December 10, 2010
Financial Amount Pledged to Date: $14,500, $20,500 needed.
Only 3 of the 13 Parishes have submitted pledge sheets to date
Gift In Kind committed: $0 (Last Time this accounted for approximately $7,000 of the budget)
Trades people need to talk to our construction manager by January 1, and have a written agreement with Habitat by January 15. The major trades (HVAC, Plumbing, and Electrical) need to be completed between January 30 and March 5 while the house is open from the demolition work days.
Schedule:
Prebuild day: January 28-29
Kickoff: March 5
Workdays: Thurs-Sat, with days assigned to Parishes
Project Length: Two Months
Questions?: Contact Maggie Porter, mporter@h4h.org, 734.677.1558, ext. 119