July 25, 2009 Update

















































































On Friday July 24, Chuck and Dennis laid addition Pergo flooring; finishing the living room and partial hallway

On Saturday with a good size crew we:

Added most all molding
Replaced one basement window
Painted molding and front exterior door
Nailed molding around tub surround and window
Installed the bathroom medicine cabinet
Finalized a few electrical connections for the electrician
Replaced rear door threshold
Added decorative molding at front door
Plugged hole in crawlspace
Fixed corner of deck
Caulked kitchen countertop
Hung interior doors
Rerouted cold air and hot air ducts in crawlspace
Installed kick plate molding in front of kitchen cabinets
Hung mailbox

The next couple of Saturdays should be minor items and clean-up

On Sunday July 25, Andrew did additional mudding on the attic opening and Ryan and Steve laid the tile on two stairs and landing by rear door.